== DECEMBER 22ND 2009 WE MOVED IN!! ==

Tuesday, 22nd of December, 2009 - Day 99 - *HOUSE IS COMPLETED*

We have now moved into our new house, exciting and yet stressful at the same time, got the keys on the 21st of December and had to pay the final cheque to the builder as well as other variations to the house. Everything was flat out busy during hand over time as we had all plumbers, electrician and other contractors installing our hot water, air con, stove and oven and other last minute touch ups.

Key Variations were
- Ducted Cooling
- Extra power points
- Telephone line exchange connection
- Garage door colour upgrade

Just a few more touch ups outside the house which can wait till next year, we will need fencing and concreting done after the new years.

Here are the final photos of the house (mostly interior), prior to moving in.

Kitchen with the cooktop and oven and rangehood


Different view of the kitchen

Kitchen Bench and location of Fridge and Pantry

View from Kitchen - Living room and Dining

Stone Bench top

Bedroom 1

Bedroom 2

Guest Bathroom, Bathtub and Shower

Hallway to Bedroom 1 and 2 and Bathroom

The living room kitchen and dining to backyard

House to the laundry and garage

Door to the laundry on the left and to the living room

Study room

Our En suite Bathroom

Our En suite and Walk in robe

Our family area or kids play area

Door to study room

Entrance to our house and our master bedroom

== DECEMBER 2009 - *** HOUSE FINISHED** ==

Wednesday, 17th of December, 2009 - Day 96 - *HOUSE IS COMPLETED*

We have been informed that the house is ready for occupancy and to be moved into, I got the final invoice and occupancy permit so everything is all well to go ahead.
I have arranged and completed final paper work with the Bank, and they have completed the valuation and now the final check can be picked up any time and trade with the builder for the keys to our house.
We have now been running around getting all of our indoor appliance ready and other things the property may need.

We have scheduled to move on Tuesday December 22nd 2009.

=======================================================================================

== DECEMBER 2009 - COMPLETION STAGES ==

Wednesday, 9th of December, 2009 - Day 89 - Fixing Stage Complete - Completion Stages

We checked the property yesterday, the fencing seems to be taken off now, and they are now working on the floorboards which means its nearly finished. Due to the rain and mud it made it difficult to look through the window. But have caught some pics inside the house.







Friday, 7th of December, 2009 - Day 87 - Fixing Stage Complete - Completion Stages

Haven't updated this for 2 months as all the stuff being done is inside and we cannot get in hence lock up complete, but the summary is that the house interior is almost complete.
Plastering has been done, the electrical's, gas, pipes, ducted cooling and heating is all placed in now.
The house has been painted, the tiling has been done, the facade has been rendered, and our garage has been placed I believe it is about 2 or 3 weeks and the house is done.
The only thing that it needs now is the boundary fencing, and driveway, but that is not important for now.

Here are the photos of the past months of our house in progress.

Front of our house has been rendered and Garage Door Placed


The backyard looking towards the 2nd bathroom

Our backyard, looking towards the kitchen

The front entrance of our house, facade has been rendered.

Our electronic panel garage

House being rendered.

As of October and November, Plastering being done.

The kitchen area of the house pipes sticking out where the bench will be

Kitchen and living area towards the backyard

Laundry area and door to the garage

The front entrance, on the right our masterbedroom

Garage being plastered

== OCTOBER 2009 - LOCK UP COMPLETE ==

Friday, 9th of October, 2009 - Day 46 - Stage 3 Lock up complete

Been busy and wasn't able to log all the entries, but during the end of September and the beginning of October. We chose the interior colour for our Kitchen, Bathroom, Shower Tiles, Ceiling and Walls.

We also had an appointment with our site manager to check for our electrical locations and the placement of the lights in the house.

The bricks have been completed and now it looks more and more better. They have completed Stage 3 which also means increase in payments. Stage 4 which is the final stage will be starting next week. Finally they will start on the interiors, plastering, kitchen benches, all the taps electrical's etc..

Photos of the progress of the Bricks are shown below.